ESKOM · E3469NTCSANGR

Establishment of Enabling Agreement for Northeast Grid - Ntcsa for the Disposal of 1 X 40MVA Transformer at Rockdale Substation on a Once-off Contract Agreement.

Mpumalanga · MiddelburgDisposals: GeneralHand deliveryCompulsory briefing

Summary

ESKOM invites bids for Establishment of Enabling Agreement for Northeast Grid - Ntcsa for the Disposal of 1 X 40MVA Transformer at Rockdale Substation on a Once-off Contract Agreement. Closes 21 October 2026 at 10:00 (15 days left). Compulsory briefing on 20 October 2026 at 11:00 at Rockdale Sub Station in Middelbueg. Bids are delivered by hand to Rockdale sub station Middelburg -Middelburg-Middelburg-1051. 12 official documents available to download.

Closing date21 October 2026 at 10:0015 days left
Briefing sessionCompulsory20 October 2026 at 11:00 · Rockdale Sub Station in Middelbueg
How to submitHand deliveryRockdale sub station Middelburg -Middelburg-Middelburg-1051
Published6 October 2026Request for Proposal

Conditions

N/A

Buyer contact

ESKOM

Ntsako Machebe
macheb@eskom.co.za
013-693-2872